Your capital budget 2027 has to be signed off, and on the list are your first electric trucks, a heat pump for the new hall or an extra production line. Before a figure goes next to any of them, answer five energy questions: does the plan fit your grid connection, how high will your peak be, which investment pushes that peak up, which battery do you actually need, and what will you do if the grid operator says no.

Answer those questions with your site’s own quarter-hourly data and an approved investment won’t stall halfway through 2027 because the connection is full. Sometimes it also turns out that a smaller set-up will do than the first quote suggested.

In brief

An investment your grid connection can’t handle stands still, however good the business case looks on paper.

  • Your connection decides what can run. Plantline opened its all-electric building on a temporary connection of 55 kW, while 320 kW had been planned for the operation.
  • Your peak counts, not your annual consumption. Two 60 kW DC fast chargers add 120 kW to your peak if they charge at the same time.
  • Solar alone won’t solve a winter peak. At Van Ommen, solar panels only helped in summer; the new hall with its spot welding line fitted the grid contract once a battery was added.
  • Size a battery before you order it. For truck dealer LVS, Elektropartners used the site’s quarter-hourly data to work out how much storage was needed.
  • Two Dutch decisions affect your business case: the government proposed raising the Energy Investment Allowance to 45.5% from 1 January 2027, and the ACM wants large consumers on regional grids to pay time-of-use transport tariffs from 1 January 2028.

Model the peak first, then fill in the figure.

Does your 2027 plan fit the grid connection you have?

You only know once you run the plan against your site’s own quarter-hourly data. The contracted capacity in your contract is the limit within which every new charger, heat pump or machine has to fit. That limit doesn’t grow with your budget.

Applying for a heavier connection is no quick way out. In its letter to the Dutch House of Representatives in June 2026, the Dutch regulator ACM wrote that expanding the grids is expected to take up to ten years on average. An investment that waits for that expansion can stand idle for years.

Plantline, a plant exporter from the Greenport Boskoop region in the Netherlands, ran into exactly this with its new, all-electric building in Hazerswoude-Dorp. All it had was a construction connection of around 55 kW, while 320 kW had been planned for the operation. Installation partner Ecopowercell installed a 466 kWh battery, and Tibo EMS controls it so the site absorbs peaks of up to 150 kW within the connection. That allowed the building to open while it waited for its full connection.

Until that connection arrived, a diesel generator stood next to the building as well. Plantline’s director, Max Hoogenboom, put the cost at €600 for maintenance every four weeks, on top of €1,500 a week in diesel. A stopgap like that appears in no capital budget, but you pay for it all the same.

Full is not the same as fully used. In practice, we see many connections hit their limit for only a few hours a month. If you know which hours those are, you can plan your investments around them.

Generated with AI

How high will your peak be, and when does it fall?

Your peak is the highest power your site draws at the same time, and it decides whether an investment fits. It isn’t how much energy you use, but how much at once. A monthly total or annual figure hides that peak: two sites with the same annual consumption can have very different peaks.

So look at your quarter-hourly values. They show at which hours and in which months your peak falls, and how close it comes to your contracted capacity. Then put your plans next to them. Two 60 kW DC fast chargers add 120 kW to your peak if they charge at the same time at the end of a shift. The same charging power often fits comfortably at night.

Go over your limit anyway and you pay for it. Read what exceeding your contracted capacity costs, and how to prevent it, in a separate article.

Which investment pushes your peak up the most?

The one that draws power at the moment your site is already at its limit. That is why the order of investments matters as much as the amount. These are the usual culprits:

  • Chargers for a fleet. Trucks and vans often return at the same time and want to charge straight away.
  • Heat pumps and cooling. They draw the most on cold mornings and warm afternoons, exactly when the rest of the site is running too. Tibo EMS only controls them via the building management system, in agreement with the building manager.
  • Production lines and welding equipment. They create short, high peaks at start-up or during welding.
  • Solar panels. They reduce what you draw during the day, but do nothing for a peak in the evening or in winter.

Van Ommen, a metalworking specialist in Beekbergen, the Netherlands, wanted a new production hall with a spot welding line in a region where the grid was full. Installer Hollander Techniek modelled the new situation first. According to adviser Bastian Hoonhorst, the current energy profile combined with the simulated future consumption created a peak too high for the grid contract.

Solar panels only solved that in summer. The expansion fitted within the existing contract once a battery was added for the winter peaks. According to Jeroen Althusius, co-founder of Tibo Energy, that covers Van Ommen for at least the next fifteen years.

Do you need a battery, and how big?

With a tight connection, often yes, but the size follows from your peak profile rather than a standard quote. A battery that’s too small won’t absorb your peak. One that’s too big ties up money you could have invested elsewhere. Modelling also shows when a smaller set-up will do.

LVS, a Volvo Trucks and Renault Trucks dealer in Broek op Langedijk, needed DC fast chargers for its growing number of electric trucks. Its contracted capacity covered day-to-day operations, but not charging. Elektropartners loaded the existing quarter-hourly data into Tibo’s simulation, together with the expected charging demand. Based on that, the site got 125 kWp of solar panels, two battery systems and two 60 kW DC fast chargers, which Tibo EMS controls within the limits of the connection.

Dennis Koopmans, project manager at Elektropartners: “We loaded the existing quarter-hourly data into Tibo’s simulation and determined the expected charging demand. Based on those outcomes, we could determine exactly how much battery storage was needed.”

The tax side counts in a budget too. In the Netherlands, batteries are on the Energy List of the Energy Investment Allowance (EIA) under certain conditions. Mind the year: according to RVO, the Energy List that applies is the one for the year in which you sign the purchase agreement or place the order. How to build a battery business case is covered in a separate article.

Batterijen-Harva-International

Generated with AI

What will you do if the grid operator says no?

Then you budget for growing within the connection you have. If you control your peak, you often don’t have to wait for a heavier connection. The money then goes into control: a battery, smart charging and a system that keeps everything within the limit.

Budget for the step after that as well. It never stops at one electric vehicle, and neither does your peak. So choose a set-up in which the next charger, battery or site joins the same system. Start small, never start over.

Tibo EMS gets solar, chargers and battery working together within the limit of your connection. The system recalculates every five minutes and plans 48 hours ahead. That interplay of assets within one limit, Energy Orchestration, also keeps your next investment manageable. The calculation your installer makes upfront becomes the configuration of the system on your site, without re-implementation. Still weighing up the two routes? Read why you should upgrade your grid connection or control it smartly depending on your situation.

Which Dutch rules and tariffs belong in your 2027 budget?

Two decisions affect the business case of every energy investment you make in the Netherlands in 2027:

  • Energy Investment Allowance up to 45.5%. In the 2027 Tax Plan, presented on Budget Day, 15 September 2026, the government proposed raising the deduction rate from 40% to 45.5% from 1 January 2027. The proposal still had to pass both chambers of the Dutch parliament. Check with your tax adviser what applies in the end.
  • Time-of-use transport tariffs from 2028. Under the draft decision published by the ACM in October 2026, large consumers on regional grids pay transport tariffs that depend on the time of day from 1 January 2028. What you buy in 2027 will run under those tariffs in 2028.

The second decision makes the question of when your peak falls even more important. What it means for charging at busy times is covered in our article on Dutch time-of-use grid tariffs.

What does your 2027 plan do to your peak?

Your installer can run your plan against your site’s quarter-hourly data before a single euro is spent. You then see, per investment, what it does to your peak, which battery fits and in what order to invest. That calculation then becomes the basis for controlling your site.

In a demo, we show how that modelling works and what Tibo EMS then handles automatically.

FAQ

For every investment that draws power, such as chargers, a heat pump or a production line, note what it does to your peak and whether that fits within your contracted capacity. If it doesn’t, include the cost of the solution as well: a battery, smart control or a heavier connection. In the Netherlands, also check whether the investment is on the Energy List, because then the Energy Investment Allowance counts.

Your quarter-hourly values for the past year, plus your plans: how many charging points, what power, and which driving schedules or production hours. The quarter-hourly values show when your peak falls. Your plans show what gets added to it.

That depends on when your peak falls. If it falls during the day in summer, solar panels help straight away. If it falls in the evening or in winter, you need a battery that charges when there is room.

Your installer, using Tibo’s software. The installer does the calculation and installs the assets. Tibo EMS then uses the same model as the configuration for controlling your site.

Have it modelled against your site’s quarter-hourly data before you sign. You’ll see whether the battery really absorbs your peak, and whether a smaller one would do.

Yes. Start with the step that helps your peak most now, and choose a set-up in which the next charger, battery or site joins the same system. Then you won’t have to start over at your next budget round.