Exceeding contracted capacity is something you usually find out about weeks later. On a Tuesday morning the compressors restart after maintenance, six electric trucks return from their runs at the same time and the new cold store is running at full power. For one quarter-hour you draw more than your contract allows. Nobody on the floor noticed.
What that quarter-hour costs depends mostly on where your connection sits. Outside a congested area, it’s a few thousand euros. Inside one, you pay in a different currency.
Going over your contracted capacity costs a few thousand euros outside a congested area. Inside one, you lose something you can’t simply buy back: room to grow.
- Your contracted transport capacity (in Dutch: gecontracteerd transportvermogen, or GTV) is the maximum you may draw under your connection and transport agreement. One quarter-hour above it counts as an exceedance.
- Worked example using Liander’s 2026 tariffs: a single 150 kW peak above an 800 kW contract costs more than €4,650, because the higher contract stays in place for at least a year.
- Since the code decision of April 2025, grid operators in congested areas no longer raise your contract automatically after an exceedance. You apply for more capacity, and then you join the queue.
- In a congested area, an exceedance puts you in default and you can be held liable for damage to the grid.
- Almost every exceedance comes down to simultaneity: loads that each fit comfortably within your contract, but ask for slightly too much at the same moment.
On a full grid, your contracted capacity decides how much room you have to grow. You want to see where you stand every quarter-hour.
What is your contracted capacity?
Your contracted transport capacity is set out in your connection and transport agreement with the grid operator. It’s the maximum power you may use on your connection, with separate values for consumption and feed-in. In practice people also call it the contract value, or simply “the GTV”.
That figure is not the same as the capacity of your connection. Your connection can often handle more than your contract allows. The reverse doesn’t work: you can never contract more than your connection can physically carry. If you need more than that, you need a heavier connection.
Your metering company records your consumption per quarter-hour. If a single quarter-hour value sits above your contract, you’ve exceeded your contracted capacity. Whether that happens at 07:15 on a busy Monday or on a Saturday afternoon makes no difference to the grid operator.

What does exceeding contracted capacity cost?
Large consumers in the Netherlands pay two capacity components for transport, among other charges: a rate per kW of contracted capacity and a rate per kW for the month’s highest peak. On Liander’s 2026 tariff sheet, the medium-voltage category (above 136 kW up to and including 2,000 kW) pays €2.29 per kW per month for the contract and €3.57 per kW per month for the monthly peak.
Outside a congested area, Liander treats an exceedance as a request to raise your contract. Your contracted capacity goes up automatically to the value of the peak, from the first day of that month. Lowering it again is in principle only possible once your contract hasn’t been raised for twelve months.
A worked example. A distribution centre has 800 kW of contracted capacity. In March, new charge points are added and consumption peaks at 950 kW for one quarter-hour.
Total: more than €4,650 for one quarter-hour. Tariffs vary by grid operator and category, so check your own grid operator’s tariff sheet. The order of magnitude stays similar.
For a business with an energy bill in the hundreds of thousands, that’s annoying but manageable. As long as you’re outside a congested area.
Different rules in a congested area
In large parts of the Netherlands the grid is full, and there the automatic increase no longer applies. In its code decision on contracted transport capacity of April 2025, the Dutch regulator ACM set out that in a congested area you can’t gain extra transport capacity by exceeding your contract. If you want more, you apply for it, like every other business in the region. In practice, grid operators had already stopped raising contracts automatically in congested areas.
That changes what an exceedance means. According to Liander, you’re then in default, the grid operator has to take measures and you’re liable. Stedin states that an exceedance can cause serious damage to the grid, with consequences for other connected customers, and that it enforces strictly.
This has already gone to court. In 2021, Liander took a wholesaler with cold stores in North Holland to court. The business had 46 kW contracted, repeatedly peaked at up to 103 kW, and was ordered by the judge to stay within its contract.
The biggest cost: growth that no longer fits
For most businesses, the real squeeze comes with the next step: twelve charge points for the new fleet, an electric boiler to replace the gas boiler, an extra production line.
It used to sort itself out through an exceedance. You went over for a month, your contract went up and you paid a little more. In a congested area that route is closed. Your application for extra capacity goes on a waiting list, and in the meantime the expansion has to fit within your current contract.
So the question shifts from “what does an exceedance cost?” to “how much room is left under my limit?”. The answer is often more generous than your annual peak suggests. That peak usually lasts only a handful of quarter-hours a year. The rest of the time, capacity sits unused that you can put to work with smart control. For more options, see our page on managing grid congestion.

Why exceedances happen
Behind an exceedance there are usually a few ordinary situations that coincide in the same quarter-hour:
None of these patterns shows up in a spreadsheet of monthly totals. You only see them in quarter-hourly data.
How to prevent exceeding your contracted capacity
Prevention starts with knowing where you stand and ends with control. These are the steps that make the most difference:
Op een spreadsheet met maandtotalen zie je geen van deze patronen. Ze worden pas zichtbaar in kwartierdata.

Generated with AI
How Tibo EMS keeps watch over your contracted capacity
Tibo EMS reads the metering data from your connection and your assets in real time. Every five minutes the system calculates a new control plan for the next 48 hours, based on expected demand, generation, energy prices and the limit of your contract. If a quarter-hour threatens to go over that limit, the system shifts charging sessions, deploys the battery or defers flexible loads.
The system works with a fixed contract value and with limits that vary over time, as with a capacity limitation contract. The dashboard shows you, day by day, how close you came to your contracted capacity. A heatmap shows whether near-exceedances fall at random or keep recurring on the same days.
At Lidl’s distribution centre in Almere, the EMS matches charging sessions to the logistics planning and controls solar, battery and grid supply in real time. That way the electrification fits within the limits of the existing connection.
An EMS can only control what’s controllable. How much room there is to gain under your limit depends on your assets and your processes. We’d rather work that out with you than promise it here.
How much room is left under your limit?
Not sure whether your expansion fits within your current contract, or seeing your peaks creep closer to your contracted capacity? In a demo we show you how Tibo EMS keeps watch over your limit and what that means for your next step. Book a demo and bring your quarter-hourly data.
Frequently asked questions