You’ve found a building that fits. Good location, enough space, a rent that sits within budget. The agent has walked you through the layout and fire safety has been checked. Nobody has asked how much electricity the building is allowed to draw.

That question usually comes up once the first electric company cars are ordered, the heating has to switch from gas to electric, or a new production line is on the way. Then it turns out the building was set up for the previous occupant, and that more capacity means joining a queue that runs for years in parts of the country. Renting commercial property in the Netherlands therefore calls for one extra check before you sign, especially if you’re new to the Dutch grid.

TL;DR

A building can have a heavy grid connection and still be allowed to use only a fraction of it.

  • Enexis moved into a building in Best with a 1,750 kVA connection and only 74 kW of contracted capacity: enough for the previous tenant, far too little for a distribution centre.
  • Requesting extra capacity in congested areas means a waiting time that can stretch to ten years.
  • Since 1 July 2026, small connections up to 3×80 amps in congested areas join the same waiting list.
  • A previous tenant who held the contract may have reduced the contracted capacity. A terminated connection often means years of waiting.
  • With your current consumption profile and your plans, you can check before signing whether you’ll fit within the connection.

Negotiate the rent without checking the capacity, and you also sign up for a ceiling on your growth.

Connection size and contracted capacity are two different numbers

A property brochure usually lists one figure: the connection size, for example 1,000 or 1,750 kilovolt-amperes (kVA). That tells you what the cable and installation can physically handle. How much of it you may actually use from the grid operator is set in the contracted transport capacity. That second figure decides what you can do in the building.

The gap can be large. When Enexis, one of the Dutch grid operators, took over a new distribution centre and maintenance workshop in Best, the building had a 1,750 kVA connection with only 74 kilowatts (kW) of contracted capacity. It was enough for the previous tenant. For a large distribution centre, it barely covered the basic facilities. You can read the full story in our case study on Enexis in Best.

With grid congestion, requesting more capacity is no quick fix. Waiting times can stretch to ten years, and this spring 15,000 large consumers were already on the waiting list for a new or heavier connection. Since 1 July 2026, Dutch grid operators no longer reserve capacity for small connections either, with a transition period until 1 January 2027. A smaller building is no longer a guarantee that an upgrade will go smoothly.

What a tight connection costs you

There’s no fixed figure. The cost items are predictable, though, and you can add them up for your own situation.

The biggest one is time. For Enexis, the choice was clear, says Jan Nijhuis, contract manager for facility management & real estate: “It was simple. Even as a grid operator, we’re just in the queue like everyone else. So either we found a way to stay within the limits of this connection, or we had to postpone the relocation. And that would have immediately slowed down our growth.”

You can run that sum yourself. What does a month of delay cost in revenue, postponed customer contracts or paying rent twice? Multiply it by the waiting time your grid operator quotes, and you know what the connection of that building should be worth to you.

Then come the investments you make afterwards, under time pressure. Solar panels, a battery or a different charging strategy can solve the problem. But if you only think of them once operations are running, you have little room left to negotiate with the landlord. In a rented building there’s also the question of who owns those installations when you leave. A landlord can argue that alterations fixed to the building belong to them, without compensation.

And there’s the capacity you can lose without noticing. If the previous tenant held the contract, they may have reduced the contracted capacity, for instance to save on fixed costs. If a connection is terminated or removed, a new application in a congested area almost always means years of waiting.

EMS CO2 reductie vastgoed: distributiecentrum met zonnepanelen en batterijopslag

Generated with AI

Renting commercial property in the Netherlands: questions to ask before you sign

You’ll get the answers from the landlord, the agent or the grid operator. It takes a few emails, and it saves you discovering the limit after you’ve moved in.

  • How much contracted transport capacity does the building have, for both consumption and feed-in? Ask for it in kW. The connection size in kVA says little about it.
  • Whose name are the connection and transport agreements in? That decides who can change or cancel the capacity, and what happens to the contract when tenants change.
  • What did the previous occupant draw over the past few years? Quarter-hourly values or monthly peaks show how close the building already ran to its limit.
  • Is the building in a congested area, and is an application for extra capacity already in progress? A pending application holds a place in the queue, and that place is worth something.
  • Are you allowed to install solar panels, a battery and charge points, where exactly, and who owns them when you leave?
  • Is there physical room? Think of a roof that can carry panels, a spot for a battery container and a distribution board that can take an expansion.

Put the answers in the lease. Have the legal side reviewed by whoever drafts your contract. For the technical side, you need an installer and a way to run the numbers.

Check your plans against the building’s connection

With those answers, you can start calculating. Take the consumption profile of your current site as a baseline, ideally in quarter-hourly values. Add what you plan to do in the new building: charge points for the electric vans arriving in two years, an extra cold store, a second production line. Then lay that profile against the contracted capacity. You’ll see when you’d cross the limit, how often and by how much.

At Enexis, installation partner Eigenenergie.net did exactly that with Tibo Energy’s simulation software. They modelled how different combinations of solar panels, batteries and EV chargers would perform in day-to-day operations. “Thanks to the models, we immediately saw what was feasible,” says Nijhuis. The result: solar on the roof, two batteries in the car park and a distribution cabinet that can handle a doubling of solar and battery capacity.

Holtkamp Horeca faced a similar choice. The croquette and patisserie producer wanted to start quickly at a new site in Nieuw-Vennep, where only 55 kW of contracted capacity was available. Too little for production. Installer Elektropartners mapped the expected consumption and ran it through the Tibo simulation tool. Daniël Keegstra of Elektropartners: “We first looked at the expected energy consumption and the peak loads. On that basis we determined the required battery capacity.” With solar panels, batteries and a back-up generator for winter, production now runs within the existing 55 kW.

In both cases, the building’s capacity was fixed before the occupant had any say in it. The difference lay in when they started calculating. How much room your own profile has to shift is covered in our article on flexible capacity.

Distributiecentrum met laadplein, zonnepanelen en batterijcontainer als illustratie van flexibel vermogen

When smart control isn’t enough

A battery moves energy in time. It doesn’t make your connection any bigger. That gives you a hard limit you can work out in advance: with 74 kW of contracted capacity, you can draw at most 1,776 kWh per day from the grid (74 kW x 24 hours). If your operation needs more energy per day than the connection plus your own generation can supply, no battery will help.

How long your peaks last matters too. A charging hub that runs at full power for eight hours every night quickly calls for a battery larger than the business case can carry. And if you’re not allowed to feed in and the roof is small, your own generation is limited as well.

If it doesn’t fit, at least you know before you’re locked in. You can walk away from the building, agree with the landlord that they apply for extra capacity and how the costs are split, or phase your electrification so you grow at the pace the connection allows. Renting commercial property in the Netherlands is a decision for years, so that choice is better made before the signature than after.

Hardware through your installer, control through Tibo EMS

If it fits with a battery or solar panels added, you need two things. The hardware comes from an installer, who designs, installs and maintains it. We work every day with some of the largest installers in the Netherlands, such as Unica and Hoppenbrouwers Techniek, and with firms like Hollander Techniek and Elektropartners. Many of them use our simulation to check a system before anything is ordered.

After that, everything has to work together within the contracted capacity. That’s the job of Tibo EMS, our Energy Management System. Every five minutes it recalculates a control schedule for the next 48 hours, based on real-time metering data, energy prices and weather forecasts. There are no fixed rules. The system continuously decides when the battery charges, when the charge points run and how consumption stays under the limit.

At Enexis, which isn’t allowed to feed power back into the grid, that forward view is what gets the battery empty or full at the right moment. Nijhuis on the result: “We use more of our own solar energy and avoid penalties for exceeding our contracted capacity.”

Still unsure whether smart control is enough in your situation? In an earlier article, we set out when an upgrade or smart control is the better choice.

Want to know whether your plans fit that building?

Have you got a building in mind, or are you already hitting the limit at your current site? With your consumption data and the connection details, we work with your installer to check what fits and what you need to make it work. In a demo, we show you how that works.

Frequently asked questions

Connection size is what the physical connection can handle, usually expressed in kVA. Contracted transport capacity is what your grid operator allows you to use, in kW. A building can have a heavy connection with a low contract, like the 1,750 kVA and 74 kW at Enexis in Best.

You can always apply, but in congested areas you’ll join a waiting list. That list is ordered under the prioritisation framework of the Netherlands Authority for Consumers and Markets (ACM), and priority doesn’t mean you’ll get capacity quickly. So work with the waiting time your grid operator quotes, and don’t assume an increase will come through before your move-in date.

That depends on who holds the contract and what happens to the agreement when tenants change. Check with the landlord and have it put in writing. Once a connection has been terminated, a new application in a congested area often takes years.

The consumption profile of your current site, ideally in quarter-hourly values, the contracted capacity of the new building and an overview of what you want to add, such as charge points, machines or cooling. If you already have solar panels or a battery in mind, include them as a scenario.

Yes. Since 1 July 2026, Dutch grid operators in congested areas no longer reserve capacity for small connections up to 3×80 amps. They join the same waiting list, with a transition period until 1 January 2027.